A Note on the Financial Evaluation of Projects

Abstract

This note provides guidance on the financial evaluation of projects. It explains in detail the various financial appraisal techniques of a project, including non-discounted and discounted cash flow techniques, with suitable explanations, formulae and numerical examples. The objective of this note is to make the reader understand the concept and applications of various financial appraisal techniques for the financial evaluation of projects.

INTRODUCTION

The project evaluation process involves more than just determining a project's expected revenues and profitability; it also involves a study of the key factors that affect a project and their financial impact on the project. In addition, a project evaluation includes strategic evaluation, economic evaluation and social impact evaluation (Refer Exhibit I). While the financial evaluation of a project aims at ascertaining the most efficient strategy for delivering the desired output, the strategic evaluation ensures that the project is consistent with the output objectives of the firm. The economic evaluation of the project, however, seeks to ensure that the delivered output is benefiting the public at large. The evaluation of social impact aims at ensuring that the consequences of a project (in terms of employment, output, savings and so on) are beneficial to the public. The financial appraisal is the most important part of the evaluation because the project cannot be successful if it is financially unviable, even though it may be technically and commercially feasible

DEFINING THE TERMS

Projects, by their definition, have a defined start and end date. A project is defined as "a collection of linked activities, carried out in an organized manner with a clearly defined start point and finish point, to achieve some specific results that satisfy the needs of an organization as derived from the current business plans." Projects are characterized by pre-determined goals, defined scope, limited resources, sequenced activities and a specific end result.

While discussing the evaluation of a project, it is important to understand some other terms that are often used. Cost of capital refers to the rate of return which must be earned by a firm in order to satisfy the expectations of the investors who provide the funds for the firm. It is measured as the weighted arithmetic average of the cost of various sources of finance obtained by the firm. Expected return is the arithmetic mean or average of all possible outcomes where those outcomes are weighted by the probability of their occurrence. The legal, printing, postage, underwriting brokerage costs, and other costs of issuing securities, are known as floatation costs. Incremental cash flow is the difference in cash flows of a firm with and without a project. It can also be defined as the change in the future cash flows of a firm as a direct consequence of undertaking a project. The value of a future stream of payments or receipts from a project when discounted at a given rate to the present time it is known as the present value of a project. Projects are said to be mutually exclusive when the acceptance of one will necessarily mean the rejection of others.

The net present value of a project is the present value of future payments reduced by the present value of costs. The rate of discount at which the net present value of an investment is zero is called the internal rate of return. Benefit cost ratio measures the present value of returns per rupee of investment. Sensitivity analysis is a risk analysis technique used for studying the responsiveness of net present value to changing a variable in the profitability equation. It is akin to 'what if' analysis. For example, we can know the impact of reduction in the costs of raw materials by 10 % on NPV of a project......

More...

FINANCIAL EVALUATION

FACTORS FOR MEASURING PROJECT CASH FLOWS

CASH FLOWS FROM LONG TERM FUNDS POINT OF VIEW

CASH FLOWS FROM EQUITY FUNDS POINT OF VIEW

CASH FLOWS FROM TOTAL FUNDS POINT OF VIEW

CHOICE OF DISCOUNT RATE

APPRAISAL CRITERIA

DISCOUNTED CASH FLOW/TIME ADJUSTED TECHNIQUES

NET PRESENT VALUE

TRADITIONAL OR NON-DISCOUNTED CRITERIA

APPRAISAL TECHNIQUES IN PRACTICE FOR VARIOUS TYPES OF PROJECTS

CAVEATS FOR IMPROVED FINANCIAL EVAULATION

CONCLUSION

EXHIBIT I : ASPECTS OF PROJECT APPRAISAL

EXHIBIT II : PROJECT EVALUATION TECHNIQUES

        Case Code   MISC009
   Case Length    
17 Pages
              Period   
 Organization    

        Pub Date     2003
Teaching Note    Not Available
     
Countries    
      
Industry   

Issues

Keywords

Financial evaluation, projects, financial appraisal, techniques, project, non-discounted, discounted cash flow, techniques, suitable explanations, formulae, numerical examples, concept, applications, financial appraisal techniques, financial evaluation, and projects.

    Business, Strategy & Management Case Studies | Miscellaneous Case Studies | Case Study on A Note on the Financial Evaluation of Projects

     To Download this case (No.      MISC009 ) click on the link  
      below, and select the case  
     from the list of available
     cases:

       » Miscellaneous Cases

       » Case Studies Collection

       » ICMR Home      

      Prices:

     For delivery in Electronic
     Format: Rs. 300

Current Exchange Rates
INR 300.00 = USD ($),
                 = GBP (£),
                 = EURO (€)
Currency data courtesy coinmill.com
INR is INDIAN RUPEES (Rs.)


     For delivery through courier
     (within India): Rs. 300 + Rs. 25
     for Shipping & Handling
     Charges

View Detailed Pricing Info
    
      


 
Google
Webicmrindia.org